The day before Formnext 2026 opened, ASTM gathered 176 people from 17 countries for an AM standards summit. The honest conclusion: 103 published standards still do not let a qualified part cross a border.
Formnext 2026 opens this week in Frankfurt with the usual wall of new machines. The most useful conference room in the city was booked a day early, under the least appealing name: the AM Innovation and Standards Summit, organized by ASTM International at the Congress Center on November 16. Around 176 people from 17 countries showed up, and the theme was the one problem no product launch solves: when does a qualified part stop being somebody else's risk?
Where the standards actually stand
ASTM's opening numbers are the useful kind of humble. There are now 103 published additive manufacturing standards across ASTM F42 and ISO/TC 261, and 74 open work items. There is also a nine million dollar US program aimed at cutting qualification barriers, including the expensive habit of repeating tests for every new site. The room heard plainly that a part qualified in Frankfurt should be trusted in Houston, Seoul or Tokyo, and today is not.
What the militaries asked for
NATO's head of standardization, Holger Ziegler, stated the alliance's approach as civil first, NATO only when necessary, and argued for a common set of documents with a clearer division of labor between civilian and military standards bodies. A German Air Force officer, Captain Lukas Hohn, then gave the concrete version. His maintenance example covers about 1,920 parts across more than 160 aircraft stands, with critical parts routed to engineering and non-critical parts treated as interim spares. The force prints PA12 parts in SLS to replace machined POM, and reported lower costs, shorter lead times and cheaper variant changes. The ask is a common NATO technical data package: drawing, CAD, installation detail, intended use, loads, vibration, the original material and the original safety factor. He also flagged the trap everyone knows: the same data on different machines can produce parts with different properties, so someone has to own the certified process chain as one unit.
The part nobody puts on a spec sheet
Software got its own breakout, and the proposals were practical: standard names for process parameters, slicing and post-processing steps; software that helps engineers find and navigate the standards they are supposed to follow; and real interfaces between vendor packages. A data management table proposed standard quality reports and automatic validation of AM data. Amsight showed why the automation push matters: a single laser powder bed fusion workflow example contained roughly 1,700 data points, of which the company estimates 95 percent of project, design and build data could be automated, against only 28 percent for in-situ monitoring.
The qualification discussion had the sharpest idea of the day. The European Space Agency proposed leaning on first-article evidence plus traceability and process monitoring to focus inspection on critical characteristics, quoting potential 50 to 70 percent cuts in recurring inspection cost. Oak Ridge National Laboratory's Michael Kirka proposed the experiment that would settle the argument: run parts across shops and countries, chosen by the authorities who approve them, and let the results show what evidence legitimately carries over to a second site. A US-UK exercise with primes and suppliers swapping countries already surfaced the dealbreakers: data rights, export controls, and who carries commercial responsibility.
An opinion
The correct lesson from this summit is ordering, not ambition. Agree first on words, measurements and report formats, because vocabulary is cheap and workforce training depends on it. Be slow about prescribing process while the process is still improving, because standards that freeze a method can freeze it below the next safety improvement. And fund Kirka's cross-site trials now, because 103 standards without evidence portability is paperwork with a cross-border stamp. The people who write standards, make parts and approve parts finally spent a day in one room. That is how it should start. It needs to not stop there.