PERI 3D Construction used a COBOD BOD2 printer to build ViliaSprint2 in Bezannes, France, delivering 12 social housing apartments and cutting the overall project timeline by three months.

PERI 3D Construction has completed ViliaSprint2 in Bezannes, France, a 12-apartment social housing project that the partners describe as Europe's largest 3D printed multi-family residential building. Developed by Plurial Novilia, a subsidiary of Action Logement, the three-story building provides 800 square meters of living space.

On-site printing at multi-family scale

ViliaSprint2 is the first building in France where both the load-bearing structure and all walls were printed directly on site. PERI 3D Construction operated a COBOD BOD2 gantry system to extrude concrete layer by layer and form the complete shell. Holcim supplied printable concrete based on its TectorPrint technology, reinforced with synthetic macro fibers and formulated within the company's CO2-reduced ECOPact range.

The printing phase began in March 2025 and finished ahead of schedule. The team credited an optimized sequence for installing prefabricated floor slabs, which reduced how often the print gantry had to be repositioned.

Measured gains against a conventional build

Plurial Novilia built a near-identical building on the same site using conventional methods, creating a direct comparison. The partners reported that the 3D printed shell took 34 effective printing days instead of the 50 originally planned, helping cut the overall project timeline by three months. Only three operators were needed for the printed shell, compared with six for the traditional structure.

Material use also improved. Waste dropped from about 10 percent to 5 percent, and the curved geometry enabled by printing saved roughly another 10 percent in concrete volume. The design includes a curved facade and rounded floorplan, features that would typically add cost with conventional formwork.

Energy features and what comes next

The finished building combines printed concrete walls with timber balcony structures, perlite insulation, 500 square meters of photovoltaic panels, and a hybrid gas and heat pump system from Atlantic Systemes. The project targets around 60 percent energy self-sufficiency in line with France's RE2020 2025 requirements.

Building on ViliaSprint2, Plurial Novilia and its partners plan a follow-on project of about 40 apartments using two 3D printers at the same time. Their goal is to reduce print time further and bring costs closer to conventional construction as the process matures.