The Japanese contractor says wire arc printing has produced the first 3D printed steel structural joints in a permitted building, holding up a curved roof at the GREEN×EXPO 2027 world exposition pavilion.

Takenaka Corporation says it has used wire arc additive manufacturing to print steel joints that now serve as structural members in a permitted building, the first application of its kind anywhere, according to the company. The joints connect the tension chords of the curved roof of the Takenaka Group's KuruKuruKuru pavilion at GREEN×EXPO 2027, the international horticultural exposition opening in Yokohama next year.

No molds, no fixtures, every joint different

WAAM melts feedstock wire with an electric arc at temperatures the company puts at roughly 5,000 to 20,000 degrees Celsius and stacks the metal layer by layer. For this roof, each joint where the curved beams meet had a different geometry. Printing from the model meant one process produced every variant with no molds and no custom jigs, which is the scenario wire arc printing is genuinely good at: low volume, high variety, complex shape.

Takenaka also built lighting into the interior of the joints, folding an ambience feature into structure because the printing freedom allowed it.

What it took to get a construction permit

Novelty alone does not get steel into a public structure. The company had an independent third-party body and a designated inspection agency review the structural design approach and the quality control methods, and the building received its construction permit. Supporting evidence included material testing, full-scale member experiments, and finite element analysis.

Takenaka frames this as a step toward material certification through third-party bodies and broader use of WAAM in building structures. Its first public WAAM structure was an upcycled bench made from scrapped rails last year. Steel joints under a permitted roof is a serious jump from a park bench.

Why it matters beyond Japan

Construction-scale metal printing has spent years making demo pieces: pavilions, bridges, art. Load-bearing connections inside a code-approved building are a different category, because the approval process had to accept the material and the process, not just the drawing. Other contractors are moving into space hardware with the same technology. The structural building case moves slower for obvious reasons, and that is exactly why this milestone is the one to watch.